MCBRIDE CONSTRUCTION RESOURCES INCORPORATED PROGRESS MEETING

 

Job Site:    Shumway Condominiums

Date:          09/29/04

 

Next Meeting: 10/06/04 @ 7:00 AM —          Shumway Construction Committee (SCC) building A and B Garage in electrical room adjacent to the building B elevator

10/06/04 @ 9.00 AM — General progress meeting in job trailer

 

CONSTRUCTION UPDATE:

 

1.   Roof work on building A, B, H — 98% complete.

 

2.   Application of common area deck coatings at building D — 95% complete

 

3.   Application of stucco finish coat on building G — 100% complete.

 

4.   Application of common area deck coatings at building G — 100% complete.

 

5.   Installation of caulking at building G— 100% complete.

 

6.   Handrail painting at building G — 95% complete

 

7.   Sheet metal installation at building F — 80% complete.

 

8.   Installation of wood siding at the third floor of building F — 90% complete.

 

9.   Application of stucco at building F — 100% complete.

 

10. Sheet metal installation at building E — 60% complete

 

11. Application of stucco scratch and brown coat E - 100% complete.

 

QUESTIONS:

 

1.   Q: Could Jan (PET) review the top of the drainage mat that is being installed in the designated planters? How shall the top of this drainage mat be terminated?

 

2.   Q: Could Jan review the drainage pipe installations at the planters of buildings C and D?

 

3.   Q: Could Jan review repair work that is to be done at the northeast corner stairs of building D?

 

4.   Q: Could Jan discuss the water leak around the gas pipe at the north wall of the garage of building B? How shall MCR proceed with this situation?

 

COMMENTS:

 

1.   None.